Project update – December 2024
The Green Volt offshore windfarm project will shortly be commencing site investigation works, in connection with the
transmission infrastructure required to connect the project to the national grid.
These works are scheduled to begin on 16 December 2024 and will continue in phases over the next five months along the consented cable route. All work will be taking place with the permission of the landowner(s).
For more information, download a copy of the newsletter using the link below.